JMJ’s work with clients produces clear measurable results, some of which are detailed in this table below. Our clients often say that JMJ brings a unique combination of personal, behavioral, and cultural change, coupled with a clear focus on measurable results.
Our site will soon be updated to include results of recents successes in leadership development, projects and organizational transformation.
Incident and Injury Free Safety® Results
|
Site and man-hours |
Owner / Contractor |
Safety performance (Pre-Initiative) |
Safety Performance (Post-initiative) |
|
Aromax 13,200,000 MH Saudi Arabia |
Saudi Chevron/CCC and local subcontractors |
N/A; JMJ worked on this project from its inception. |
RIR<0.05 3 OSHA Recordables (13 million hours) |
|
Shell GOAL 6,000,000 MH U.S |
Shell/Fluor and local subcontractors |
Local sub contractor safety performance averages RIR 2.0 |
RIR<0.3 Shell and Fluor have deemed this project to be world class |
|
Dow Argentina: 5,000,000+ total MH
- EPE Project
- Cracker Project
- Medium Projects
|
Dow/FluorDaniel and local Contractors |
Average OSHA RIR for Argentinean Construction Contractors is 19.0 |
- RIR<0.45
- RIR<0.40
- RIR<0.60
|
|
Chevron Richmond NOx 700,000 MH U.S. |
Chevron/Cherne and local subcontractors |
RIR: 2.0 |
25 months Injury-Free (700,000 hours) |
|
Typhoon Offshore 210,000 MH U.S. |
ChevronTexaco Deepwater BU /McDermott |
Fab Yard injury rate was one injury per week |
Fab Yard experienced only one injury over six months. Hook-up and commissioning was completed without any recordable injuries. |
|
Seeboard UK (a subsidiary of EDF Energy) |
Seeboard Southeastern UK Electric Utility |
N/A |
55% reduction in serious injuries. |
ChevronTexaco California Refining Safety Results
|
Project Description |
Results |
- Capital Projects at both
Richmond and El Segundo Refineries
- Project System
- Large and Small projects
- Multiple contractors
- Multiple Chevron PMs
- Work inside existing facilities
|
- 18 months/2.0 Million + work hours
- 3 injuries
- 2000/2001 RIR = 2.0 (before JMJ)
- Current work RIR = 0.15 (after JMJ)
- Improved relationships
- Improved cooperation
- Improved employee morale
|
High Performance Project Results
|
Project |
Results |
|
Chevron Pascagoula Aromax |
- 13% under budget
- 3 months early
- Recognized by Business Round Table
|
|
BP PT Peni Merak Works (Indonesia) |
- 12 % under A/R
- 33% under Conceptual Estimate
- Ramp up completed 1 month early
|
|
Mobil Beaumont Paraxylene |
- 10% under budget
- 5 months early on a 33 month schedule
|
|
Arco Gawain |
|
|
Interconnector 220 K Pipeline Project – UK to Belgium |
- Completed under budget and within deadline ($249 million with original budget of $340 million)
|
|